Facility: |
Union Station District Line |
| Agency ID: |
AF052A, FDT25A |
From: |
|
| Complete: |
|
To: |
|
| Description: |
| The Metropolitan Branch Trail project will provide a 6.25-mile bicycle/pedestrian trail from Union Station north to the District Line along the railroad right-of-way. This trail will connect at the District line with a route continuing into Silver Spring MD. This project is intended to serve both recreational users and commuters to meet Transportation Control Measures (TCMs) and air quality objectives.
a. L & M St.
b. Ft. Totten |
| Amendment\Admin. Mod. |
Amendment Name |
Approved |
Resolution |
| Admin. Mod. |
Additional Funding for ROW |
12/20/2012 |
|
| Add $250,000 of CMAQ funds to Phase 2 (ROW, temporary construction easement acquisition) in FY2013. |
|
|
CMAQ 80/20/0 | |
$250
|
|
$500
$300
$5,000
|
|
|
|
$6,050 |
DEMO 80/20/0 | |
|
$3,000
| |
|
|
|
$3,000 |
| Grand Total: $9,050 |
|